Security Camera & Electronic Access Control System Modernization Project - Curry General Hospital & Curry Medical Center


Curry Health Network is seeking proposals from qualified contractors for a Security Camera and Electronic Access Control System Modernization project at Curry General Hospital in Gold Beach and Curry Medical Center in Brookings.

The project includes installation of 133 new security cameras, integration of existing surveillance equipment, and modernization and expansion of electronic access control systems at both facilities. Additional work includes specialized door hardware, accessibility controls, and supporting technology infrastructure, utilizing Genetec Security Center as the unified security management platform.

The RFQ is available to download here.

Timeline (updated 11/20/2026) Changes are shown in bold text.
Deadline for submission of questions: Nov. 20, 2026 @ 3 pm
Addendum/Responses issued: Nov. 23, 2026 @ 5 pm
Proposals due: Dec. 2, 2026 @ 3 pm
Anticipated notice of intent to award: Dec. 4, 2026
Desire project start: As soon as practicable following contract execution
Proposed project duration: To be provided by contractor

Timeline: dates subject to change at the sole discretion of Curry Health Network
Deadline for submission of questions: Nov. 20, 2026 @ 3 pm
Addendum/Responses issued: Nov. 23, 2026 @ 5 pm
Proposals due: Nov. 25, 2026 @ 3 pm
Anticipated notice of intent to award: Nov. 27, 2026
Desire project start: As soon as practicable following contract execution
Proposed project duration: To be provided by contractor

Addendum # 1 - Responses & Supporting Documents - published Nov. 23, 2026

Domestic Water Piping System Replacement - Curry Medical Center


Curry Health Network is seeking proposals from contractors interested in bidding on a project to replace the domestic water piping system at Curry Medical Center, an approximate 43,000 sf healthcare facility in Brookings, OR. CPVC piping will be replaced with new copper distribution mains and PEX branch piping from the mains to user points, while maintaining operations within an active healthcare facility.

The RFQ is available to download here.

Supplemental documents can be downloaded below:
OHA Functional Program
OHA Safety Risk Assessment
Plumbing Permit Set
Addendum # 1 Compiled Project Manual (added 10/20/2026)
Addendum # 2 (added 10/21/2026)
Addendum # 3 (added 11/04/2026)

Additionally, as of 11/4/206, the updated schedule follows (changes are reflected in bold text).

●Anticipated RFP release: October 7, 2026
●Contractor Project walk: October 20, 2026 @ 11 am
* Deadline for Submission of Questions: October 26, 2026 @ 5:00 pm
●Addendum / Responses Issued: November 4, 2026 @ 5:00 pm
●Proposals Due: November 13, 2026 @ 5:00 pm

●Interviews (If needed): Week of November 16, 2026
●Anticipated Notice of Intent to Award: November 20, 2026
●Desired Construction Start: January 04-11, 2027 (or as soon as practicable)
●Proposed Construction Duration: To be provided by Proposer
●Target Substantial Completion: May 31, 2027
●Target Final Completion: June 15, 2027


Timeline: dates subject to change at the sole discretion of Curry Health Network
Contractor project walk: Oct. 20, 2026 @ 11 am
Deadline for submission of questions: Oct. 23, 2026 @ 5 pm
Addendum/Responses issued: Oct. 30, 2026 @ 5 pm
Proposals due: Nov. 6, 2026 @ 5 pm
Anticipated notice of intent to award: Nov. 20, 2026
Desire construction start: Jan. 4-11, 2027 (or as soon as practicable)
Target substantial completion: May 31, 2027